126722GENERAL NOTICE24/04/2025 03:59:43 PM

Release of QNI limit from NSW to Qld - 29th April 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 124749.

AEMO, Transgrid, Powerlink have reviewed the test results following the QNI minor testing on 16th February 2025. The next hold point can now be released.

The hold point of 950 MW from NSW to Qld will be implemented as of 1000 hrs 29th April 2025.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
126721MARKET INTERVENTION24/04/2025 04:00:43 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126720


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 24/04/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0130 hrs 25/04/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1530 hrs 25/04/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
126720MARKET INTERVENTION24/04/2025 04:00:33 PM

Direction - SA region 24/04/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/04/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 24/04/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
126719MARKET INTERVENTION24/04/2025 02:50:53 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126714

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 25/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 24/04/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
126718MARKET INTERVENTION24/04/2025 05:08:42 PM

Cancellation - AEMO Intervention Event - SA region 23/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 23/04/2025

Refer to Market Notice 126702

The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 24/04/2025.


Manager NEM Real Time Operations
     
126717MARKET INTERVENTION24/04/2025 05:08:24 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126709

Direction is cancelled from: 1700 hrs 24/04/2025

Manager NEM Real Time Operations
     
126716MARKET INTERVENTION24/04/2025 03:22:40 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126710

Direction is cancelled from: 1530 hrs 24/04/2025

Manager NEM Real Time Operations
     
126715NON-CONFORMANCE24/04/2025 01:55:19 PM

NON-CONFORMANCE Region SA1 Thursday, 24 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 24 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 24/04/2025 13:50 to 24/04/2025 13:55
Amount: 143 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126714MARKET INTERVENTION24/04/2025 01:26:54 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126713

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 25/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage


Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm