125649RESERVE NOTICE14/03/2025 05:17:28 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 14/03/2025 to 1800 hrs 14/03/2025.
The forecast capacity reserve requirement is 1729 MW.
The minimum capacity reserve available is 1629 MW.


Manager NEM Real Time Operations
     
125647INTER-REGIONAL TRANSFER14/03/2025 05:11:12 PM

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.

The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125631RESERVE NOTICE14/03/2025 03:24:31 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125598 is cancelled at 1400 hrs 14/03/2025

AEMO Operations
     
125629RESERVE NOTICE14/03/2025 03:24:35 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125599 has been updated at 1400 hrs 14/03/2025 to the following:

From 1700 hrs to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 1432 MW.
The minimum capacity reserve available is 1319 MW.

AEMO Operations
     
125627MARKET SYSTEMS14/03/2025 02:13:15 PM

CHG0101257 - Frequency Performance Payments Release

Change Number: CHG0101257

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments Release
Change Start Date & Time: 19/03/2025 08:00:00
Change End Date & Time: 20/03/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Delivery of Frequency Performance Payments (FPP) calculation results via the participant data model may be periodically delayed during the change window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
125621INTER-REGIONAL TRANSFER14/03/2025 06:03:13 AM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125620INTER-REGIONAL TRANSFER14/03/2025 06:03:11 AM

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125599RESERVE NOTICE13/03/2025 03:02:59 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1930 hrs 16/03/2025.
The forecast capacity reserve requirement is 1728 MW.
The minimum capacity reserve available is 1129 MW.

AEMO Operations
     
125598RESERVE NOTICE13/03/2025 03:02:59 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1900 hrs 15/03/2025.
The forecast capacity reserve requirement is 1613 MW.
The minimum capacity reserve available is 1540 MW.

AEMO Operations
     