PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124091 has been updated at 1620 hrs 04/02/2025 to the following:
[1.] From 1630 hrs 04/02/2025 to 1730 hrs 04/02/2025.
The forecast capacity reserve requirement is 1699 MW.
The minimum capacity reserve available is 978 MW.
[2.] From 1830 hrs 04/02/2025 to 2000 hrs 04/02/2025.
The forecast capacity reserve requirement is 1649 MW.
The minimum capacity reserve available is 947 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1730 hrs to 2100 hrs 11/02/2025.
The forecast capacity reserve requirement is 414 MW.
The minimum capacity reserve available is 344 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124000 has been updated at 1400 hrs 04/02/2025 to the following:
1. From 1430 hrs to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1830 hrs to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 898 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124059 has been updated at 1420 hrs 04/02/2025 to the following:
[1.] From 1530 hrs 04/02/2025 to 1630 hrs 04/02/2025.
The forecast capacity reserve requirement is 1663 MW.
The minimum capacity reserve available is 1277 MW.
[2.] From 1830 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1652 MW.
The minimum capacity reserve available is 974 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025
At 0449 hrs 04/02/2025 there was an unplanned outage of South Morang - Dederang No.1 330kV line series capacitor.
The following constraint set(s) invoked at 0505 hrs 04/02/2025
V-SMSC
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124049 has been updated at 0400 hrs 04/02/2025 to the following:
[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1703 MW.
The minimum capacity reserve available is 1136 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1795 MW.
The minimum capacity reserve available is 1191 MW.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 03/02/2025
Update - Non-credible contingency event - TAS region - 03/02/2025
Refer AEMO Electricity Market Notice 124043
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: TAS
Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 03/02/2025
Non-credible contingency event - TAS region - 03/02/2025
At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations