NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025
NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 30/03/2025 21:45 to 30/03/2025 23:30
Amount: 26 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025
NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 30/03/2025 17:25 to 30/03/2025 20:15
Amount: -40 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025
NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 30/03/2025 15:45 to 30/03/2025 18:15
Amount: -113 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 30/03/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_56FB4FDD from 1405 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025
NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 30/03/2025 04:40 to 30/03/2025 04:50
Amount: -24 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 29 March 2025
NON-CONFORMANCE QLD1 Region Saturday, 29 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CALL_B_2
Duration: 29/03/2025 16:55 to 29/03/2025 17:00
Amount: -11 MW
Constraint: NC-Q_CALL_B_2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Mullumbimby - Dunoon - Lismore 132 kV 9U6 line - NSW region - 29/03/2025
Inter-regional transfer limit variation - Mullumbimby - Dunoon - Lismore 132 kV 9U6 line - NSW region - 29/03/2025
At 0427 hrs 29/03/2025 there was an unplanned outage of Mullumbimby - Dunoon - Lismore 132 kV 9U6 line.
The following constraint set(s) invoked at 0435 hrs 29/03/2025
N-LSDU_9U6
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update to Victorian system normal Kerang voltage stability limit
AEMO has completed a review of a system normal voltage stability limit in north west Victoria as a result of commissioning of BESS at Koorangie. The revised limit manages pre-contingent flow on the Wemen to Koorangie 220 kV line to avoid voltage collapse at Koorangie, Kerang or Wemen on loss of the Crowlands to Bulgana to Horsham or Horsham to Murra Warra to Kiamal 220 kV line. The revised constraint equation includes the generators in south-west NSW and north-west Victoria on the left-hand side as well as Murraylink and V-SA. Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit will be implemented at 0900 hrs on Monday 31st March 2025, by updating V^^V_NIL_KGTS.
For full details on the factors this constraint equation has now been loaded into AEMO's pre-production systems.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations
Inter-regional transfer limit variation - Hazelwood -South Morang No.1 500 kV line - VIC region - 27/03/2025
Inter-regional transfer limit variation - Hazelwood -South Morang No.1 500 kV line - VIC region - 27/03/2025
At 1150 hrs 27/03/2025 there was a short notice outage of Hazelwood -South Morang No.1 500 kV line.
The following constraint set(s) invoked at 1150 hrs 27/03/2025
V-HWSM
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations