Market Notices

122947MARKET INTERVENTION07/01/2025 02:22:54 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 122945

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 08/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 07/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
122945MARKET INTERVENTION07/01/2025 02:08:00 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 08/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
122933PRICES SUBJECT TO REVIEW07/01/2025 10:25:24 AM

[EventId:202501071030_review] Prices for interval 07-Jan-2025 10:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1025 hrs on 7 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jan-2025 10:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122932PRICES SUBJECT TO REVIEW07/01/2025 10:20:26 AM

[EventId:202501071025_review] Prices for interval 07-Jan-2025 10:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 7 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jan-2025 10:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122930PRICES SUBJECT TO REVIEW07/01/2025 10:15:24 AM

[EventId:202501071020_review] Prices for interval 07-Jan-2025 10:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1015 hrs on 7 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jan-2025 10:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122929PRICES SUBJECT TO REVIEW07/01/2025 10:10:22 AM

[EventId:202501071015_review] Prices for interval 07-Jan-2025 10:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1010 hrs on 7 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jan-2025 10:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122928PRICES SUBJECT TO REVIEW07/01/2025 10:05:20 AM

[EventId:202501071010_review] Prices for interval 07-Jan-2025 10:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 7 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jan-2025 10:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122925PRICES SUBJECT TO REVIEW07/01/2025 10:00:20 AM

[EventId:202501071005_review] Prices for interval 07-Jan-2025 10:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 7 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jan-2025 10:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122920INTER-REGIONAL TRANSFER07/01/2025 03:36:39 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 07/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_5687999A from 0330 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     