[EventId:202412031510_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 15:10
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 3 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1510 hrs on 3 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412031300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 December 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 3 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Refer to market notice: 121415
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 3 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412031145_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 11:45
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 3 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1145 hrs on 3 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NEM Local Temperature Alerts for SA from 03 Dec 2024 to 07 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 5th Dec, 6th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
Refer AEMO Electricity Market Notice 121376
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 1420 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_ML invoked from 1350 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Manager NEM Real Time Operations
[EventId:202412021330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 December 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 2 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 December 2024.
Refer to market notice: 121358
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 2 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412021105_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 December 2024 11:05
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 2 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1105 hrs on 2 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NEM Local Temperature Alerts for SA from 02 Dec 2024 to 06 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 5th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning