125366MARKET SYSTEMS07/03/2025 03:01:51 PM

Inital - CHG0101876 - Pre-Prod eMDM Hotfix Maintenance Release

Change Number: CHG0101876

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Hotfix Maintenance Release
Change Start Date & Time: 12/03/2025 13:00:00
Change End Date & Time: 12/03/2025 17:00:00
Outage Start Date & Time: 12/03/2025 13:00:00
Outage End Date & Time: 12/03/2025 17:00:00

Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
     
125357INTER-REGIONAL TRANSFER07/03/2025 07:27:37 AM

Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025

At 0720 hrs 07/03/2025 there was an unplanned outage of Lismore SVC.

The following constraint set(s) invoked at 0725 hrs 07/03/2025
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125356INTER-REGIONAL TRANSFER07/03/2025 06:44:20 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 125355.

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 and 2 cables of Directlink .

The following constraint set was invoked at 0620 hrs 07/03/2025

N-X_MBTE_3

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
125319PRICES SUBJECT TO REVIEW06/03/2025 01:30:16 PM

[EventId:202503061335_review] Prices for interval 06-Mar-2025 13:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125318PRICES SUBJECT TO REVIEW06/03/2025 01:25:21 PM

[EventId:202503061330_review] Prices for interval 06-Mar-2025 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125317PRICES SUBJECT TO REVIEW06/03/2025 01:20:21 PM

[EventId:202503061325_review] Prices for interval 06-Mar-2025 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125316PRICES SUBJECT TO REVIEW06/03/2025 01:15:24 PM

[EventId:202503061320_review] Prices for interval 06-Mar-2025 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125314PRICES SUBJECT TO REVIEW06/03/2025 01:10:23 PM

[EventId:202503061315_review] Prices for interval 06-Mar-2025 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125313PRICES SUBJECT TO REVIEW06/03/2025 01:05:23 PM

[EventId:202503061310_review] Prices for interval 06-Mar-2025 13:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs