125543INTER-REGIONAL TRANSFER12/03/2025 07:03:39 AM

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.

The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125521NON-CONFORMANCE11/03/2025 11:55:21 AM

NON-CONFORMANCE Region NSW1 Tuesday, 11 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 11 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 11/03/2025 11:25 to 11/03/2025 11:55
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125518INTER-REGIONAL TRANSFER11/03/2025 10:05:53 AM

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

At 0917 hrs 11/03/2025 there was an unplanned outage of Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line.

The following constraint set(s) invoked at 0925 hrs 11/03/2025
S-KNPW and S-PWSE.

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125474NON-CONFORMANCE10/03/2025 01:05:17 PM

NON-CONFORMANCE Region QLD1 Monday, 10 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 10 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/03/2025 13:00 to 10/03/2025 13:05
Amount: -11 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125357INTER-REGIONAL TRANSFER07/03/2025 07:27:37 AM

Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025

At 0720 hrs 07/03/2025 there was an unplanned outage of Lismore SVC.

The following constraint set(s) invoked at 0725 hrs 07/03/2025
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125356INTER-REGIONAL TRANSFER07/03/2025 06:44:20 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 125355.

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 and 2 cables of Directlink .

The following constraint set was invoked at 0620 hrs 07/03/2025

N-X_MBTE_3

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
125353NON-CONFORMANCE07/03/2025 01:00:15 AM

NON-CONFORMANCE Region QLD1 Friday, 7 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 7 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CPP_4
Duration: 07/03/2025 00:30 to 07/03/2025 01:00
Amount: -21 MW
Constraint: NC-Q_CPP_4

Auto-generated on behalf of Manager NEM Real Time Operations
     
125320NON-CONFORMANCE06/03/2025 01:35:23 PM

NON-CONFORMANCE Region VIC1 Thursday, 6 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 6 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 06/03/2025 13:20 to 06/03/2025 13:35
Amount: 9 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125312INTER-REGIONAL TRANSFER06/03/2025 11:29:23 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No. 1 and 2 Legs of Directlink.

The following constraint set was invoked at 1125 hrs 06/03/2025.

N-X_MBTE_3

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     