123354POWER SYSTEM EVENTS15/01/2025 10:45:07 PM

Non-credible contingency event - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 15/01/2025

At 2019 hrs the Tomago - Taree (963) 132kV line and the Tomago - Brandy Hill (96C) 132kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of disconnection of 80 MW of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123256NON-CONFORMANCE15/01/2025 10:15:26 AM

NON-CONFORMANCE Region QLD1 Wednesday, 15 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 15 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/01/2025 09:50 to 15/01/2025 10:15
Amount: 15 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
123245NON-CONFORMANCE15/01/2025 05:15:14 AM

NON-CONFORMANCE Region QLD1 Wednesday, 15 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 15 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/01/2025 02:40 to 15/01/2025 05:15
Amount: -28 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
123238NON-CONFORMANCE15/01/2025 02:05:18 AM

NON-CONFORMANCE Region QLD1 Wednesday, 15 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 15 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/01/2025 01:45 to 15/01/2025 02:05
Amount: 32 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
123237NON-CONFORMANCE15/01/2025 12:05:15 AM

NON-CONFORMANCE Region QLD1 Wednesday, 15 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 14 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 14/01/2025 23:05 to 15/01/2025 00:05
Amount: 17 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123222NON-CONFORMANCE14/01/2025 06:05:19 PM

NON-CONFORMANCE Region NSW1 Tuesday, 14 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 14 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 14/01/2025 18:00 to 14/01/2025 18:05
Amount: -108 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
123194NON-CONFORMANCE14/01/2025 06:00:15 AM

NON-CONFORMANCE Region NSW1 Tuesday, 14 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 14 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 14/01/2025 05:55 to 14/01/2025 06:00
Amount: -19 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123182NON-CONFORMANCE13/01/2025 07:20:16 PM

NON-CONFORMANCE Region NSW1 Monday, 13 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 13 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 13/01/2025 19:10 to 13/01/2025 19:20
Amount: -8 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123156NON-CONFORMANCE13/01/2025 01:50:19 PM

NON-CONFORMANCE Region QLD1 Monday, 13 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 13 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 13/01/2025 11:35 to 13/01/2025 13:50
Amount: 57 MW
Constraint: NC-Q_MPP_1