124069SETTLEMENTS RESIDUE04/02/2025 01:15:58 PM

[EventId:202502041300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 February 2025 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 4 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Refer to market notice: 124064

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 4 February 2025.

This is an AEMO autogenerated Market Notice.
     
124066RESERVE NOTICE04/02/2025 12:57:51 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1830 hrs 07/02/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 576 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124064SETTLEMENTS RESIDUE04/02/2025 11:35:33 AM

[EventId:202502041135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124062RESERVE NOTICE04/02/2025 09:04:57 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124061 is cancelled at 0800 hrs 04/02/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
124061RESERVE NOTICE04/02/2025 07:52:40 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1500 hrs 05/02/2025.
The forecast capacity reserve requirement is 976 MW.
The minimum capacity reserve available is 908 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124060INTER-REGIONAL TRANSFER04/02/2025 05:11:43 AM

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

At 0449 hrs 04/02/2025 there was an unplanned outage of South Morang - Dederang No.1 330kV line series capacitor.

The following constraint set(s) invoked at 0505 hrs 04/02/2025
V-SMSC

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124052RESERVE NOTICE03/02/2025 05:19:25 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124042 is cancelled at 1715 hrs 03/02/2025.

Manager NEM Real Time Operations
     
124047CONSTRAINTS04/02/2025 09:32:40 AM

Update to system strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 121468

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
The system normal equations have been revised to remove Gladstone >=1 requirement.

A revision to the constraint equations will be implemented at 1200 hrs on Tuesday 4th February 2025.

The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.

The constraint equation in the Q-NIL set of the form below will be modified:

-Q_NIL_STRGTH_xxxx
-Q_NIL_STRGTH_xxxx_I

AEMO Operations
     
124042RESERVE NOTICE03/02/2025 01:56:10 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 243 MW.

AEMO is seeking a market response.

Manager NEM Real Time Operations
     