Inter-regional transfer limit variation - Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
Inter-regional transfer limit variation -Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
The outage has been completed and Collector - Marulan (4) 330 kV line returned to service at 0825 hrs 06/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 6 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 06/02/2025 01:25 to 06/02/2025 04:30
Amount: -44 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025
NON-CONFORMANCE NSW1 Region Wednesday, 5 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 05/02/2025 23:15 to 06/02/2025 00:25
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025
Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025
A planned outage of Collector WF to Marulan No. 4 330 kV Line in the NSW region was scheduled from 0600 hrs 02/02/2025 to 1600 hrs 19/02/2025.
The outage has been completed and Collector WF to Marulan No. 4 330 kV Line returned to service at 1710 hrs 04/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 4 February 2025
NON-CONFORMANCE QLD1 Region Tuesday, 4 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 04/02/2025 15:50 to 04/02/2025 16:00
Amount: 35 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 4 February 2025
NON-CONFORMANCE NSW1 Region Tuesday, 4 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 04/02/2025 12:05 to 04/02/2025 12:15
Amount: -57 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025
At 0449 hrs 04/02/2025 there was an unplanned outage of South Morang - Dederang No.1 330kV line series capacitor.
The following constraint set(s) invoked at 0505 hrs 04/02/2025
V-SMSC
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 3 February 2025
NON-CONFORMANCE NSW1 Region Monday, 3 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.
The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA
The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations