Market Notices

123442MARKET INTERVENTION18/01/2025 02:25:19 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123407

Direction is cancelled from: 1430 hrs 18/01/2025

Manager NEM Real Time Operations
     
123441MARKET INTERVENTION18/01/2025 12:26:56 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123439


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1230 hrs 18/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0000 hrs 19/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 19/01/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
123440MARKET INTERVENTION18/01/2025 12:28:12 PM

Direction - SA region 18/01/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 18/01/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1235 hrs on 18/01/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
123439MARKET INTERVENTION18/01/2025 08:10:48 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 123438

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 19/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1230 hrs 18/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
123438MARKET INTERVENTION18/01/2025 07:46:08 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 19/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
123408MARKET INTERVENTION17/01/2025 02:52:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123385

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123407MARKET INTERVENTION17/01/2025 02:50:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123384

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1430 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123403GENERAL NOTICE17/01/2025 10:51:11 AM

NEM Local Temperature Alerts for SA, VIC from 17 Jan 2025 to 21 Jan 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 19th Jan

VIC
Mildura Ap (39+ Deg C): 20th Jan, 21st Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123400GENERAL NOTICE16/01/2025 10:15:45 PM

Network Augmentation Commissioned - Vic Region - 16/01/2025

AEMO ELECTRICITY MARKET NOTICE


Network Augmentation Commissioned - Vic Region - 16/01/2025

At 2128 hrs 16/01/2025, the Koorangie 220 kV Terminal Station has been cut in to the existing Kerang - Wemen 220 kV transmission line resulting in the following network augmentations being commissioned:

Koorangie 220 kV Terminal Station
Koorangie - Wemen 220 kV transmission line
Kerang - Koorangie 220 kV transmission line

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm