NON-CONFORMANCE Region NSW1 Tuesday, 4 February 2025
NON-CONFORMANCE NSW1 Region Tuesday, 4 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 04/02/2025 12:05 to 04/02/2025 12:15
Amount: -57 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, TAS, VIC from 04 Feb 2025 to 08 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 6th Feb
TAS
Launceston Ti Tree Bend (33+ Deg C): 4th Feb
VIC
Latrobe Valley Ap (39+ Deg C): 4th Feb
Mildura Ap (39+ Deg C): 4th Feb, 6th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 05/02/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update to system strength requirements in North Queensland
Refer to market notice 121468
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
The system normal equations have been revised to remove Gladstone >=1 requirement.
A revision to the constraint equations will be implemented at 1200 hrs on Tuesday 4th February 2025.
The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.
The constraint equation in the Q-NIL set of the form below will be modified:
-Q_NIL_STRGTH_xxxx
-Q_NIL_STRGTH_xxxx_I
AEMO Operations
NON-CONFORMANCE Region NSW1 Monday, 3 February 2025
NON-CONFORMANCE NSW1 Region Monday, 3 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, TAS, VIC from 03 Feb 2025 to 07 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 3rd Feb
Clare High School (39+ Deg C): 3rd Feb
Mt Gambier Ap (39+ Deg C): 3rd Feb
Port Augusta Ap (39+ Deg C): 3rd Feb, 4th Feb, 6th Feb
TAS
Launceston Ti Tree Bend (33+ Deg C): 3rd Feb, 4th Feb
VIC
Mildura Ap (39+ Deg C): 4th Feb, 6th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Cancellation - AEMO Intervention Event - SA region 01/02/2025
Cancellation - AEMO Intervention Event - SA region 01/02/2025
Refer to Market Notice 123988
The AEMO Intervention Event and all associated directions are cancelled from 0900 hrs on 02/02/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123989
Direction is cancelled from: 0900 hrs 02/02/2025
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123988
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 01/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0030 hrs 02/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1130 hrs 02/02/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations