PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 06/01/2025 to 1730 hrs 06/01/2025.
The forecast capacity reserve requirement is 1036 MW.
The minimum capacity reserve available is 982 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 122850
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0200 hrs 06/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1500 hrs 05/01/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122853 has been updated to the following:
[1.] From 1530 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 992 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122852 is cancelled at 1345 hrs 05/01/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1530 hrs 06/01/2025 to 1630 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1044 MW.
[2.] From 1800 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1146 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 06/01/2025 to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 922 MW.
The minimum capacity reserve available is 825 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0200 hrs 06/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122848 is cancelled at 1225 hrs 05/01/2025.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122847 has been updated at 1030 hrs 05/01/2025 to the following:
[1.] From 1700 hrs 06/01/2025 to 1730 hrs 06/01/2025.
The forecast capacity reserve requirement is 895 MW.
The minimum capacity reserve available is 859 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations