Filter by category
Filter by Date
[EventId:204] AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 09 March 2025
ADMINISTERED PRICE PERIOD DECLARED in SA1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the SA1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,573,700.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1805 hrs on 09 March 2025 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the SA1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125424 is cancelled at 1200 hrs 09/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 09/03/2025 to 1930 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 617 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 08/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125374 is cancelled at 1345 hrs 08/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 09/03/2025 to 1930 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 593 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the SA region - 12/02/2025
Cancellation of Actual (LOR2) condition in the SA region - 12/02/2025
The Actual LOR2 Condition in the SA Region advised in AEMO Electricity Market Notice No.124573 is cancelled at 1940 hrs 12/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 12/02/2025
Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 12/02/2025
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR2 condition is forecast to exist until 1930 hrs
The capacity reserve required is 245 MW
The minimum reserve available is 107 MW
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124290 has been updated to the following:
[1.] From 1630 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1034 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1185 MW.
Manager NEM Real Time Operations