Update - AEMO market notice 125439 was published in error: AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Refer market notice 125439 and 125440
AEMO confirms that market notice 125439 was published in error.
An ADMINISTERED PRICE PERIOD has NOT been triggered in SA1 region.
Manager NEM Real Time Operations
AEMO market notice 125439 was published in error: AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Refer market notice 125439
AEMO believes market notice 125439 was published in error.
We believe an ADMINISTERED PRICE PERIOD has NOT been triggered in SA1 region.
AEMO is currently reviewing the event and will update the market as soon as possible.
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 09 March 2025
Manager NEM Real Time Operations
[EventId:204] AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 09 March 2025
ADMINISTERED PRICE PERIOD DECLARED in SA1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the SA1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,573,700.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1805 hrs on 09 March 2025 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the SA1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the suspect Lack Of Reserve Level 2 (LOR2) condition in the QLD Region on 13/02/2025
The suspect LOR2 condition advised in AEMO Electricity Market Notice No. 124585 has been reviewed.
AEMO considers this forecast LOR2 condition invalid
No LOR2 condition is currently forecast for the QLD region.
Manager NEM Real Time Operation
PDPASA - Suspect Lack Of Reserve Level 2 (LOR2) in the QLD Region on 13/02/2025
AEMO considers that there is a suspect Forecast LOR2 condition for the QLD region for the following period[s]:
[1.] From 1830 hrs 13/02/2025 to 1930 hrs 13/02/2025.
The forecast capacity reserve requirement is 639 MW.
The minimum capacity reserve available is 480 MW.
AEMO is currently investigating this LOR2 forecast condition to confirm whether they are valid.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124235 is cancelled at 1200 hrs 06/02/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124230 has been updated at 1000 hrs 06/02/2025 to the following:
From 1600 hrs to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1092 MW.
The minimum capacity reserve available is 574 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124224 is cancelled at 0840 hrs 06/02/2025.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124221 has been updated at 0424 hrs 06/02/2025 to the following:
From 1500 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 907 MW.
The minimum capacity reserve available is 685 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations