122216RECLASSIFY CONTINGENCY18/12/2024 06:54:22 PM

Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Cancellation time: 18/12/2024 18:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 122189

Auto-generated on behalf of Manager NEM Real Time Operations
     
122215RECLASSIFY CONTINGENCY18/12/2024 06:49:20 PM

Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Cancellation time: 18/12/2024 18:49

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 122193

Auto-generated on behalf of Manager NEM Real Time Operations
     
122208PRICES SUBJECT TO REVIEW18/12/2024 06:40:24 PM

[EventId:202412181845_review] Prices for interval 18-Dec-2024 18:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 18 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 18:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122207PRICES SUBJECT TO REVIEW18/12/2024 06:35:22 PM

[EventId:202412181840_review] Prices for interval 18-Dec-2024 18:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 18 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 18:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122206PRICES SUBJECT TO REVIEW18/12/2024 06:30:23 PM

[EventId:202412181835_review] Prices for interval 18-Dec-2024 18:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 18 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 18:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122205PRICES SUBJECT TO REVIEW18/12/2024 06:25:17 PM

[EventId:202412181830_review] Prices for interval 18-Dec-2024 18:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 18 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 18:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122204PRICES SUBJECT TO REVIEW18/12/2024 06:20:16 PM

[EventId:202412181825_review] Prices for interval 18-Dec-2024 18:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1820 hrs on 18 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 18:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122203PRICES SUBJECT TO REVIEW18/12/2024 06:15:16 PM

[EventId:202412181820_review] Prices for interval 18-Dec-2024 18:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 18 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 18:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122202SETTLEMENTS RESIDUE18/12/2024 06:00:28 PM

[EventId:202412181800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 18 December 2024 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 18 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 December 2024.

Refer to market notice: 122200

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 18 December 2024.