Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124254
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 10/02/2025.
The direction update is issued at 1415 hrs 08/02/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124255
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 10/02/2025.
The direction update is issued at 1415 hrs 08/02/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025
NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124254
PPCCGT PELICAN POINT at 0730 hrs 07/02/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 09/02/2025.
The direction update is issued at 1410 hrs 07/02/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124255
TORRB2 TORRENS ISLAN at 0730 hrs 07/02/2025 to Remain synchronised and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/02/2025.
The direction update is issued at 1410 hrs 07/02/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 7 February 2025
NON-CONFORMANCE NSW1 Region Friday, 7 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 07/02/2025 03:40 to 07/02/2025 03:50
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 6 February 2025
NON-CONFORMANCE QLD1 Region Thursday, 6 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KINGASF1
Duration: 06/02/2025 14:55 to 06/02/2025 16:15
Amount: 29 MW
Constraint: NC-Q_KINGASF1
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124253
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1500 hrs 06/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/02/2025 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124253
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1510 hrs 06/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/02/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations