[EventId:202411270945_confirmed] Prices for interval 27-Nov-2024 09:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 November 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 09:45.
In accordance with Market Notice 121033 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411271005_confirmed] Prices for interval 27-Nov-2024 10:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 November 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 10:05.
In accordance with Market Notice 121039 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411271000_confirmed] Prices for interval 27-Nov-2024 10:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 November 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 10:00.
In accordance with Market Notice 121037 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411270955_confirmed] Prices for interval 27-Nov-2024 09:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 November 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 09:55.
In accordance with Market Notice 121035 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411270950_confirmed] Prices for interval 27-Nov-2024 09:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 November 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 09:50.
In accordance with Market Notice 121034 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 121013 is cancelled at 0900 hrs 27/11/2024.
No LOR2 condition is currently forecast in the STPASA period in the QLD region.
AEMO Operations
Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Palmerston - Hadspen 3 & 4 110kV and
Duration: 27/11/2024 09:15 until further notice
Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Duration: 27/11/2024 08:30 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121015 has been updated at 0900 hrs 27/11/2024 to the following:
From 1530 hrs to 1830 hrs 29/11/2024.
The forecast capacity reserve requirement is 1357 MW.
The minimum capacity reserve available is 965 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations