Market Notices

123615POWER SYSTEM EVENTS23/01/2025 03:09:25 AM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123613

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: NSW

Elements: Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
Duration: 0250 hrs 23/01/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
123613POWER SYSTEM EVENTS23/01/2025 03:02:44 AM

Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 23/01/2025

At 0240 hrs the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines tripped and auto reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123587RESERVE NOTICE22/01/2025 05:07:10 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123581 has been updated at 1650 hrs to the following:

From 1800 hrs 22/01/2025 to 1930 hrs 22/01/2025.
The forecast capacity reserve requirement is 856 MW.
The minimum capacity reserve available is 709 MW.

Manager NEM Real Time Operations
     
123582MARKET INTERVENTION22/01/2025 04:01:56 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123506


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 22/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 23/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 23/01/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
123581RESERVE NOTICE22/01/2025 03:50:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1830 hrs 22/01/2025 to 1900 hrs 22/01/2025.
The forecast capacity reserve requirement is 856 MW.
The minimum capacity reserve available is 809 MW.


Manager NEM Real Time Operations
     
123580MARKET INTERVENTION23/01/2025 03:40:17 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123529

Direction is cancelled from: 0400 hrs 23/01/2025

Manager NEM Real Time Operations
     
123579MARKET INTERVENTION22/01/2025 03:58:22 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123528

TORRB3 TORRENS ISLAN at 0800 hrs 21/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/01/2025.

The direction update is issued at 1600 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123550NON-CONFORMANCE22/01/2025 09:00:31 AM

NON-CONFORMANCE Region NSW1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 22/01/2025 08:50 to 22/01/2025 09:00
Amount: 18 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123547NON-CONFORMANCE22/01/2025 06:45:21 AM

NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     