Market Notices

121114SETTLEMENTS RESIDUE27/11/2024 05:45:17 PM

[EventId:202411271745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 17:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 27 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Refer to market notice: 121112

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 27 November 2024.

This is an AEMO autogenerated Market Notice.
     
121112SETTLEMENTS RESIDUE27/11/2024 05:30:25 PM

[EventId:202411271730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 27 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 27 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121111SETTLEMENTS RESIDUE27/11/2024 05:03:44 PM

[EventId:202411271700_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 17:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 27 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Refer to market notice: 121093

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1700 hrs on 27 November 2024.

This is an AEMO autogenerated Market Notice.
     
121106RESERVE NOTICE27/11/2024 04:50:52 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121089 has been updated at 1645 hrs to the following:

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 859 MW.

Manager NEM Real Time Operations
     
121093SETTLEMENTS RESIDUE27/11/2024 03:06:53 PM

[EventId:202411271505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 15:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 27 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 27 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121089RESERVE NOTICE27/11/2024 02:48:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.

The Actual LOR1 condition is forecast to exist until 1630 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 710 MW.

Manager NEM Real Time Operations
     
121085SETTLEMENTS RESIDUE27/11/2024 02:20:22 PM

[EventId:202411271420_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 14:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 27 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Refer to market notice: 121081

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1420 hrs on 27 November 2024.

This is an AEMO autogenerated Market Notice.
     
121081SETTLEMENTS RESIDUE27/11/2024 01:32:33 PM

[EventId:202411271330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 27 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 27 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121052NON-CONFORMANCE27/11/2024 10:26:35 AM

NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 27/11/2024 09:45 to 27/11/2024 10:25
Amount: 36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm