124231NON-CONFORMANCE06/02/2025 04:31:43 AM

NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 6 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 06/02/2025 01:25 to 06/02/2025 04:30
Amount: -44 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
124230RESERVE NOTICE06/02/2025 04:26:21 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124221 has been updated at 0424 hrs 06/02/2025 to the following:

From 1500 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 907 MW.
The minimum capacity reserve available is 685 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124229NON-CONFORMANCE06/02/2025 12:25:20 AM

NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 5 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 05/02/2025 23:15 to 06/02/2025 00:25
Amount: -20 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
124224RESERVE NOTICE05/02/2025 10:19:55 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 06/02/2025 to 1930 hrs 06/02/2025.
The forecast capacity reserve requirement is 926 MW.
The minimum capacity reserve available is 692 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
124221RESERVE NOTICE05/02/2025 09:42:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124183 has been updated at 2133 hrs 05/02/2025 to the following:

From 1730 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1108 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124219RESERVE NOTICE05/02/2025 08:37:04 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124200 is cancelled at 2019 hrs 05/02/2025.

Manager NEM Real Time Operations
     
124200RESERVE NOTICE05/02/2025 05:52:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1214 MW

Manager NEM Real Time Operations
     
124183RESERVE NOTICE05/02/2025 04:17:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124154 has been updated at 1500 hrs 05/02/2025 to the following:

From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1162 MW.
The minimum capacity reserve available is 842 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124180GENERAL NOTICE05/02/2025 03:16:32 PM

Update - Vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 124044
At 1410 hrs 03/02/2025 the Farrell - Reece No.1 and No.2 220 kV lines lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Farrell - Reece No.1 and No.2 220 kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     