[EventId:202502071735_review] Prices for interval 07-Feb-2025 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 7 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502071730_review] Prices for interval 07-Feb-2025 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 7 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502071725_review] Prices for interval 07-Feb-2025 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 7 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502071720_review] Prices for interval 07-Feb-2025 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 7 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 936 MW
Manager NEM Real Time Operations
[EventId:202502071715_review] Prices for interval 07-Feb-2025 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 7 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502071710_review] Prices for interval 07-Feb-2025 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 7 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0101145 | Production | Planned Maintenance to Norwest Internet Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet Router
Change Start Date & Time: 15/02/2025 10:00:00 AEST
Change End Date & Time: 15/02/2025 15:00:00 AEST
Outage Start Date & Time: 15/02/2025 11:00:00 AEST
Outage End Date & Time: 15/02/2025 13:00:00 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 1 Hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10 for Policy Based VPN and 202.44.78.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
B2B VPN - Up to 1 hour outage to TNSPs with B2B VPN to AEMO NSW Datacentre if VPN connection is only terminating in NSW only.
SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.
GASHUB: Nil
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point 202.44.76.10 for Policy Based VPN and 202.44.76.12 for Route Based VPN) prior to this scheduled outage.
*** Failure to do so will impact connectivity to Marketnet Services. ***
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NEM Local Temperature Alerts for SA, VIC from 07 Feb 2025 to 11 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 11th Feb
Clare High School (39+ Deg C): 11th Feb
Mt Gambier Ap (39+ Deg C): 11th Feb
Port Augusta Ap (39+ Deg C): 10th Feb, 11th Feb
VIC
Mildura Ap (39+ Deg C): 7th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning