Market Notices

125696RESERVE NOTICE16/03/2025 07:17:11 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125671 has been updated to the following:

From 1630 hrs 16/03/2025 to 1930 hrs 16/03/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 880 MW.


Manager NEM Real Time Operations
     
125692RESERVE NOTICE15/03/2025 06:36:39 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/03/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125691 is cancelled at 1835 hrs 15/03/2025.

Manager NEM Real Time Operations
     
125691RESERVE NOTICE15/03/2025 05:42:35 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/03/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1642 MW
The minimum capacity reserve available is 1550 MW

Manager NEM Real Time Operations
     
125690RECLASSIFY CONTINGENCY15/03/2025 05:33:25 PM

Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Cancellation time: 15/03/2025 17:33

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 125672

Auto-generated on behalf of Manager NEM Real Time Operations
     
125678RESERVE NOTICE15/03/2025 04:34:10 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 15/03/2025 to 1830 hrs 15/03/2025.
The forecast capacity reserve requirement is 1663 MW.
The minimum capacity reserve available is 1546 MW.

Manager NEM Real Time Operations
     
125672RECLASSIFY CONTINGENCY15/03/2025 03:52:55 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 15/03/2025 15:52 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
125671RESERVE NOTICE15/03/2025 02:49:39 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125665 has been updated to the following:

[1.] From 1630 hrs 16/03/2025 to 1900 hrs 16/03/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1062 MW.

Manager NEM Real Time Operations
     
125668RECLASSIFY CONTINGENCY15/03/2025 02:24:15 PM

Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Cancellation time: 15/03/2025 14:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 125663

Auto-generated on behalf of Manager NEM Real Time Operations
     
125665RESERVE NOTICE15/03/2025 01:48:58 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1630 hrs 16/03/2025 to 1900 hrs 16/03/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1106 MW.


Manager NEM Real Time Operations
     