124200RESERVE NOTICE05/02/2025 05:52:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1214 MW

Manager NEM Real Time Operations
     
124190MARKET SYSTEMS05/02/2025 04:23:24 PM

CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release

Change Number: CHG0100111

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MDM - Meter Data Management_PreProd

Change Title: Pre-Prod eMDM February Maintenance Release

Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
124189MARKET INTERVENTION05/02/2025 04:36:17 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 124165

Direction is cancelled from: 1630 hrs 05/02/2025

Manager NEM Real Time Operations
     
124182MARKET INTERVENTION05/02/2025 03:58:42 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124097


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 05/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 06/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1300 hrs 06/02/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
124181POWER SYSTEM EVENTS05/02/2025 03:22:35 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124044

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will cancel the reclassification of this event as a credible contingency event.

Manager NEM Real Time Operations
     
124179RESERVE NOTICE05/02/2025 02:54:25 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124176 is cancelled at 1444 hrs 05/02/2025.

Manager NEM Real Time Operations
     
124176RESERVE NOTICE05/02/2025 02:04:22 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1330 hrs.
The Actual LOR1 condition is forecast to exist until 1430 hrs

The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1254 MW

Manager NEM Real Time Operations
     
124165MARKET INTERVENTION05/02/2025 01:18:56 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 124096

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 05/02/2025.

The direction update is issued at 1315 hrs 05/02/2025.

Manager NEM Real Time Operations
     
124137RESERVE NOTICE04/02/2025 07:50:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124131 is cancelled at 1930 hrs 04/02/2025.

Manager NEM Real Time Operations
     