[EventId:202503221750_confirmed] Prices for interval 22-Mar-2025 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 22 March 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Mar-2025 17:50.
In accordance with Market Notice 125875 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503221810_confirmed] Prices for interval 22-Mar-2025 18:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 22 March 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Mar-2025 18:10.
In accordance with Market Notice 125880 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503221805_confirmed] Prices for interval 22-Mar-2025 18:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 22 March 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Mar-2025 18:05.
In accordance with Market Notice 125878 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503221800_confirmed] Prices for interval 22-Mar-2025 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 22 March 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Mar-2025 18:00.
In accordance with Market Notice 125877 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503221755_confirmed] Prices for interval 22-Mar-2025 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 22 March 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Mar-2025 17:55.
In accordance with Market Notice 125876 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503221745_confirmed] Prices for interval 22-Mar-2025 17:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 22 March 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Mar-2025 17:45.
In accordance with Market Notice 125874 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 22/03/2025 17:05 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Duration: 22/03/2025 17:05 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Duration: 22/03/2025 16:44 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations