Update - AEMO market notice 125439 was published in error: AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Refer market notice 125439 and 125440
AEMO confirms that market notice 125439 was published in error.
An ADMINISTERED PRICE PERIOD has NOT been triggered in SA1 region.
Manager NEM Real Time Operations
AEMO market notice 125439 was published in error: AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Refer market notice 125439
AEMO believes market notice 125439 was published in error.
We believe an ADMINISTERED PRICE PERIOD has NOT been triggered in SA1 region.
AEMO is currently reviewing the event and will update the market as soon as possible.
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 09 March 2025
Manager NEM Real Time Operations
[EventId:204] AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 09 March 2025
ADMINISTERED PRICE PERIOD DECLARED in SA1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the SA1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,573,700.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1805 hrs on 09 March 2025 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the SA1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
Non-credible contingency event - NSW region - 07/03/2025
Non-credible contingency event - NSW region - 07/03/2025
At 0612 hrs the following plant tripped.
Lismore132 - Mullumbimby 9U6 132kV Line
Lismore132 - Mullumbimby 9U7 132kV Line
Ewingsdale - Mullumbimby 9G5 132kV Line
No 1 and 2 cables of Directlink
AEMO did not instruct load shedding.
Approximately 7MW of bulk electrical load has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 7 March 2025
NON-CONFORMANCE QLD1 Region Friday, 7 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CPP_4
Duration: 07/03/2025 00:30 to 07/03/2025 01:00
Amount: -21 MW
Constraint: NC-Q_CPP_4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Thursday, 6 March 2025
NON-CONFORMANCE VIC1 Region Thursday, 6 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 06/03/2025 13:20 to 06/03/2025 13:35
Amount: 9 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 5 March 2025
NON-CONFORMANCE QLD1 Region Wednesday, 5 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 05/03/2025 17:35 to 05/03/2025 17:45
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 05/03/2025
Update - Non-credible contingency event - NSW region - 05/03/2025
Refer AEMO Electricity Market Notice 125268
At 1400 hrs the Directlink DC1 was returned to service.
(At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line was returned to service.)
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 5 March 2025
NON-CONFORMANCE NSW1 Region Wednesday, 5 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 05/03/2025 12:00 to 05/03/2025 12:25
Amount: -120 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations