Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/03/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/03/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1699 MW
The minimum capacity reserve available is 1528 MW
Manager NEM Real Time Operations
[EventId:202503141620_review] Prices for interval 14-Mar-2025 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503141615_review] Prices for interval 14-Mar-2025 16:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1610 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503141610_review] Prices for interval 14-Mar-2025 16:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503141605_review] Prices for interval 14-Mar-2025 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503141600_review] Prices for interval 14-Mar-2025 16:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1555 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503141555_review] Prices for interval 14-Mar-2025 15:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1550 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 15:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503141550_review] Prices for interval 14-Mar-2025 15:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 15:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0101257 - Frequency Performance Payments Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments Release
Change Start Date & Time: 19/03/2025 08:00:00
Change End Date & Time: 20/03/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Delivery of Frequency Performance Payments (FPP) calculation results via the participant data model may be periodically delayed during the change window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.