Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126458 is cancelled at 1845 hrs 09/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1549 MW
The minimum capacity reserve available is 1164 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 09/04/2025 to 1800 hrs 09/04/2025.
The forecast capacity reserve requirement is 1519 MW.
The minimum capacity reserve available is 1500 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025.
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126441 is cancelled at 1440 hrs 09/04/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 10/04/2025 to 1830 hrs 10/04/2025.
The forecast capacity reserve requirement is 1581 MW.
The minimum capacity reserve available is 1580 MW.
Manager NEM Real Time Operations
Update to Victorian system normal Kerang voltage stability limit
AEMO has completed a review of a system normal voltage stability limit in north west Victoria as a result of commissioning of BESS at Koorangie. The revised limit manages pre-contingent flow on the Wemen to Koorangie 220 kV line to avoid voltage collapse at Koorangie, Kerang or Wemen on loss of the Crowlands to Bulgana to Horsham or Horsham to Murra Warra to Kiamal 220 kV line. The revised constraint equation includes the generators in south-west NSW and north-west Victoria on the left-hand side as well as Murraylink and V-SA. Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit will be implemented at 0900 hrs on Monday 31st March 2025, by updating V^^V_NIL_KGTS.
For full details on the factors this constraint equation has now been loaded into AEMO's pre-production systems.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations
Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025
Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125715 is cancelled at 1915 hrs 16/03/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The forecast capacity reserve requirement is 1684 MW.
The minimum capacity reserve available is 1242 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125700 has been updated at1415 hrs to the following:
[1.] From 1700 hrs 16/03/2025 to 1930 hrs 16/03/2025.
The forecast capacity reserve requirement is 1720 MW.
The minimum capacity reserve available is 1162 MW.
Manager NEM Real Time Operations