122826RESERVE NOTICE04/01/2025 04:38:33 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122823 has been updated at 0430 hrs 04/01/2025 to the following:

From 1430 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1228 MW.
The minimum capacity reserve available is 603 MW.
AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122824NON-CONFORMANCE03/01/2025 10:15:14 PM

NON-CONFORMANCE Region QLD1 Friday, 3 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 3 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 03/01/2025 21:35 to 03/01/2025 22:15
Amount: -57 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122823RESERVE NOTICE03/01/2025 09:36:20 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122818 has been updated at 2130 hrs 03/01/2025 to the following:

From 1430 hrs 06/01/2025 to 2030 hrs 06/01/2025.
The forecast capacity reserve requirement is 1336 MW.
The minimum capacity reserve available is 535 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122818RESERVE NOTICE03/01/2025 06:38:11 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122810 has been updated at 1830 hrs 03/01/2025 to the following:

From 1430 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1298 MW.
The minimum capacity reserve available is 427 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122810RESERVE NOTICE03/01/2025 04:40:51 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122772 has been updated at 1630 hrs 03/01/2025 to the following:

[1.] From 1430 hrs 06/01/2025 to 1600 hrs 06/01/2025.
The forecast capacity reserve requirement is 1149 MW.
The minimum capacity reserve available is 700 MW.

[2.] From 1630 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 488 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122772RESERVE NOTICE03/01/2025 04:27:51 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122736 has been updated at 0430 hrs 03 Jan 2025 to the following:

[1.] From 1700 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 577 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122736RESERVE NOTICE02/01/2025 03:27:28 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122733 has been updated at 1500 hrs 02/01/2025 to the following:

From 1700 hrs to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 578 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
122733RESERVE NOTICE02/01/2025 03:01:43 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122697 has been updated at 1400 hrs 02/01/2025 to the following:

From 1530 hrs to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 297 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
122699RECALL GEN CAPACITY02/01/2025 08:36:19 AM

Request for Generator Recall Information for the period 06/01/2025 for Region NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 122697.

Please provide Generator Recall Information for the period 06/01/2025, by 1200 hrs on 03/01/2025 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm