[EventId:202412031145_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 11:45
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 3 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1145 hrs on 3 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412030705_review] Prices for interval 03-Dec-2024 07:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 07:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030700_review] Prices for interval 03-Dec-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030655_review] Prices for interval 03-Dec-2024 06:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0650 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030650_review] Prices for interval 03-Dec-2024 06:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0645 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030645_review] Prices for interval 03-Dec-2024 06:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0640 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030640_review] Prices for interval 03-Dec-2024 06:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0635 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121384 is cancelled at 1920 hrs 02/12/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1066 MW
Manager NEM Real Time Operations