[EventId:202501221350_review] Prices for interval 22-Jan-2025 13:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 13:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501221345_review] Prices for interval 22-Jan-2025 13:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 13:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501221340_review] Prices for interval 22-Jan-2025 13:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 13:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Wednesday, 22 January 2025
NON-CONFORMANCE NSW1 Region Wednesday, 22 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 22/01/2025 08:50 to 22/01/2025 09:00
Amount: 18 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025
NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 22/01/2025
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123540 is cancelled at 0615 hrs 22/01/2025
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 22/01/2025 to 1900 hrs 22/01/2025.
The forecast capacity reserve requirement is 884 MW.
The minimum capacity reserve available is 810 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 January 2025
NON-CONFORMANCE NSW1 Region Tuesday, 21 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TALWA1
Duration: 21/01/2025 18:35 to 21/01/2025 18:40
Amount: 44 MW
Constraint: NC-N_TALWA1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 123471 is cancelled at 1400 hrs 21/01/2025.