Request for Generator Recall Information for the period 27/11/2024 for Region NSW
Refer to AEMO Electricity Market Notice no. 120894, and 120892.
Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120886 has been updated at 0445 hrs 25/11/2024 to the following:
[1.] From 1500 hrs 27/11/2024 to 1530 hrs 27/11/2024.
The forecast capacity reserve requirement is 895 MW.
The minimum capacity reserve available is 331 MW.
[2.] From 1700 hrs 27/11/2024 to 2200 hrs 27/11/2024.
The forecast capacity reserve requirement is 880 MW.
The minimum capacity reserve available is 294 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
[1.] From 1330 hrs 28/11/2024 to 1530 hrs 28/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 414 MW.
[2.] From 1600 hrs 28/11/2024 to 1700 hrs 28/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 593 MW.
[3.] From 1730 hrs 28/11/2024 to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 696 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120880 has been updated at 0415 hrs 25/11/2024 to the following:
[2.] From 0730 hrs 27/11/2024 to 1130 hrs 27/11/2024.
The forecast capacity reserve requirement is 1373 MW.
The minimum capacity reserve available is 89 MW.
[3.] From 1930 hrs 27/11/2024 to 0000 hrs 28/11/2024.
The forecast capacity reserve requirement is 1411 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 24/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 24/11/2024
The Actual LOR1 Condition in the NSW region advised in AEMO Electricity Market Notice No.120889 is cancelled at 1845 hrs 24/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1541 MW
The minimum capacity reserve available is 1460 MW
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120868 has been updated at 1630 hrs 24/11/2024 to the following:
[1.] From 1730 hrs 27/11/2024 to 2130 hrs 27/11/2024.
The forecast capacity reserve requirement is 737 MW.
The minimum capacity reserve available is 300 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120873 has been updated at 1445 hrs 24/11/2024 to the following:
[1.] From 1400 hrs 26/11/2024 to 2330 hrs 26/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 47 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120874 has been updated at 1445 hrs 24/11/2024 to the following:
[1.]From 0930 hrs 27/11/2024 to 1200 hrs 27/11/2024.
The forecast capacity reserve requirement is 1181 MW.
The minimum capacity reserve available is 239 MW.
[2.] From 1900 hrs 27/11/2024 to 2300 hrs 27/11/2024.
The forecast capacity reserve requirement is 1078 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations