123589RESERVE NOTICE22/01/2025 05:47:39 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 854 MW
The minimum capacity reserve available is 543 MW

Manager NEM Real Time Operations
     
123588INTER-REGIONAL TRANSFER22/01/2025 05:29:02 PM

Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 25/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region (Northern NSW) , AEMO has invoked constraint set #N-Q-MNSP1_E from 1720 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1

Manager NEM Real Time Operations
     
123587RESERVE NOTICE22/01/2025 05:07:10 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123581 has been updated at 1650 hrs to the following:

From 1800 hrs 22/01/2025 to 1930 hrs 22/01/2025.
The forecast capacity reserve requirement is 856 MW.
The minimum capacity reserve available is 709 MW.

Manager NEM Real Time Operations
     
123581RESERVE NOTICE22/01/2025 03:50:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1830 hrs 22/01/2025 to 1900 hrs 22/01/2025.
The forecast capacity reserve requirement is 856 MW.
The minimum capacity reserve available is 809 MW.


Manager NEM Real Time Operations
     
123554INTER-REGIONAL TRANSFER22/01/2025 10:40:43 AM

Inter-regional transfer limit variation -Bundy-Buronga (6F) 330 kV line - NSW region - 21/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - - NSW region - 21/01/2025

At 1935 hrs 21/01/2025 there was a short notice outage of Bundy-Buronga (6F) 330 kV line

The following constraint set(s) invoked
I-BDBU_ONE

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,VIC1-NSW1,V-SA,T-V-MNSP1

The outage is scheduled to return to service at 1935 hrs 22/01/2025

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123552GENERAL NOTICE22/01/2025 10:59:15 AM

NEM Local Temperature Alerts for QLD, SA from 22 Jan 2025 to 26 Jan 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Dalby Ap (37+ Deg C): 22nd Jan, 23rd Jan, 24th Jan

SA
Port Augusta Ap (39+ Deg C): 26th Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123551GENERAL NOTICE22/01/2025 10:28:28 AM

Update - Pre dispatch demand forecast error - NEM regions

AEMO ELECTRICITY MARKET NOTICE

Update - Pre dispatch demand forecast error - NEM regions

Refer market notice: 123548

The issue relating to the Pre dispatch demand forecast error has been resolved.

Manager NEM Real Time Operations
     
123548GENERAL NOTICE22/01/2025 07:55:01 AM

Pre dispatch demand forecast error - NEM regions

AEMO ELECTRICITY MARKET NOTICE

Pre dispatch demand forecast error - NEM regions

AEMO is aware of an error in the Pre dispatch demand forecast for the NEM regions
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.


Manager NEM Real Time Operations
     
123545RESERVE NOTICE22/01/2025 06:27:05 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123540 is cancelled at 0615 hrs 22/01/2025