121530RESERVE NOTICE06/12/2024 04:44:35 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121529 is cancelled at 1645 hrs 06/12/2024.

Manager NEM Real Time Operations
     
121529RESERVE NOTICE06/12/2024 04:20:58 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121527 has been updated at 1620 hrs to the following:

[1.] From 1730 hrs 06/12/2024 to 1800 hrs 06/12/2024.
The forecast capacity reserve requirement is 1643 MW.
The minimum capacity reserve available is 1610 MW.

Manager NEM Real Time Operations
     
121527RESERVE NOTICE06/12/2024 03:55:14 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1630 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1626 MW.
The minimum capacity reserve available is 1296 MW.

Manager NEM Real Time Operations
     
121504RESERVE NOTICE06/12/2024 01:25:11 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1724 MW.
The minimum capacity reserve available is 1675 MW.

Manager NEM Real Time Operations
     
121438RESERVE NOTICE03/12/2024 05:30:53 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 03/12/2024 to 1830 hrs 03/12/2024.
The forecast capacity reserve requirement is 1573 MW.
The minimum capacity reserve available is 1541 MW.

Manager NEM Real Time Operations
     
121424RESERVE NOTICE03/12/2024 02:30:08 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121414 is cancelled at 1415 hrs 03/12/2024.

Manager NEM Real Time Operations
     
121416RESERVE NOTICE03/12/2024 12:44:49 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121406 is cancelled at 1215 hrs 03/12/2024.

Manager NEM Real Time Operations
     
121414RESERVE NOTICE03/12/2024 11:24:50 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121405 has been updated at 1115 hrs to the following:

[1.] From 1330 hrs 03/12/2024 to 1600 hrs 03/12/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 1081 MW.

Manager NEM Real Time Operations
     
121406RESERVE NOTICE03/12/2024 08:09:47 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 03 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 121386 has been updated at 0750 hrs to the following:

[1.] From 1800 hrs 03/12/2024 to 1930 hrs 03/12/2024.
The forecast capacity reserve requirement is 1127 MW.
The minimum capacity reserve available is 991 MW.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm