PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 05/02/2025 to 1530 hrs 05/02/2025.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1353 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124131 is cancelled at 1930 hrs 04/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1161 MW
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124119 has been updated at 1715 hrs 04/02/2025 to the following:
[1.] From 1730 hrs 04/02/2025 to 2000 hrs 04/02/2025.
The forecast capacity reserve requirement is 1639 MW.
The minimum capacity reserve available is 1108 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124091 has been updated at 1620 hrs 04/02/2025 to the following:
[1.] From 1630 hrs 04/02/2025 to 1730 hrs 04/02/2025.
The forecast capacity reserve requirement is 1699 MW.
The minimum capacity reserve available is 978 MW.
[2.] From 1830 hrs 04/02/2025 to 2000 hrs 04/02/2025.
The forecast capacity reserve requirement is 1649 MW.
The minimum capacity reserve available is 947 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 4 February 2025
NON-CONFORMANCE QLD1 Region Tuesday, 4 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 04/02/2025 15:50 to 04/02/2025 16:00
Amount: 35 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502041540_review] Prices for interval 04-Feb-2025 15:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 4 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 15:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502041535_review] Prices for interval 04-Feb-2025 15:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 4 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 15:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502041530_review] Prices for interval 04-Feb-2025 15:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1525 hrs on 4 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 15:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.