Market Notices

125561POWER SYSTEM EVENTS12/03/2025 02:12:35 PM

Update - Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/03/2025

Refer AEMO Electricity Market Notice 125555

Updated elements: Sheffield George Town No. 1 220kV Line, Sheffield George Town No. 2 220kV Line plus 40 MW load loss at Nystar and 56 MW load loss at Temco.

Manager NEM Real Time Operations
     
125556POWER SYSTEM EVENTS12/03/2025 01:24:46 PM

Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 12/03/2025

At 1200 hrs the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie 2 110kV Line and the Ulverstone - Emu Bay 110kV Line tripped.

AEMO did not instruct load shedding.

AEMO has been advised that 43MW of bulk electrical load has been disconnected.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125555POWER SYSTEM EVENTS12/03/2025 12:58:00 PM

Update - Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/03/2025

Refer AEMO Electricity Market Notice 125554

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Sheffield George Town No. 1 220kV Line and Sheffield George Town No. 2 220kV Line
Duration: 1300 hrs 12/03/2025 until further notice
Constraint set(s) invoked: T-GTSH_N-2

Manager NEM Real Time Operations
     
125554POWER SYSTEM EVENTS12/03/2025 12:24:04 PM

Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 12/03/2025

At 1158 hrs the Sheffield George Town No. 1 220kV Line and the Sheffield George Town No. 2 220kV Line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125550POWER SYSTEM EVENTS12/03/2025 09:47:07 AM

Update - Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/03/2025

Refer AEMO Electricity Market Notice 125548

At 09:29 hrs the Burnie - Smithton Tee Port Latta No. 1 110kV Line and the Burnie - Smithton Tee Port Latta No. 2 110kV Line tripped and auto-reclosed (2nd event).

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Burnie - Smithton Tee Port Latta No. 1 110kV Line and Burnie - Smithton Tee Port Latta No. 2 110kV Line
Duration: 0940 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
125548POWER SYSTEM EVENTS12/03/2025 09:46:32 AM

Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 12/03/2025

At 0909 hrs the Burnie -Smithton Tee Port Latta No. 1 110kV Line and the Burnie -Smithton Tee Port Latta No. 2 110kV Line tripped and auto-reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125517POWER SYSTEM EVENTS11/03/2025 10:05:23 AM

Non-credible contingency event - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 11/03/2025

At 0917 hrs the Penola West - South East 132 kV line and the Kincraig - Penola West 132 kV line tripped.

AEMO did not instruct load shedding.

Approximately 3 MW of electrical load has been disconnected.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
125452RESERVE NOTICE09/03/2025 08:16:22 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125446 is cancelled at 2015 hrs 09/03/2025.

Manager NEM Real Time Operations
     
125446RESERVE NOTICE09/03/2025 07:11:28 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1930 hrs 09/03/2025 to 2030 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 600 MW.


Manager NEM Real Time Operations
     