PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 02/12/2024 to 1830 hrs 02/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1247 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121302 has been updated at 1040 hrs 01/12/2024 to the following:
[1.] From 1630 hrs 02/12/2024 to 1700 hrs 02/12/2024.
The forecast capacity reserve requirement is 968 MW.
The minimum capacity reserve available is 732 MW.
[2.] From 1730 hrs 02/12/2024 to 1830 hrs 02/12/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 833 MW.
AEMO is seeking a market response.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121302 has been updated at 0900 hrs 01/12/2024 to the following:
[1.] From 1600 hrs 02/12/2024 to 1900 hrs 02/12/2024.
The forecast capacity reserve requirement is 1097 MW.
The minimum capacity reserve available is 762 MW.
AEMO is seeking a market response.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1700 hrs 02/12/2024 to 1730 hrs 02/12/2024.
The forecast capacity reserve requirement is 1330 MW.
The minimum capacity reserve available is 1071 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1600 hrs 02/12/2024 to 1630 hrs 02/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1327 MW.
[2.] From 1700 hrs 02/12/2024 to 1730 hrs 02/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1346 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121241 is cancelled at 1400 hrs 03/12/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024
Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024
A planned outage of Red Cliffs - Wemen 220 kV line in the VIC region was scheduled from 0400 hrs 30/11/2024 to 1430 hrs 30/11/2024.
The outage has been completed and Red Cliffs - Wemen 220 kV line returned to service at 1120 hrs 30/11/2024
Constraint set(s) revoked: V-KG_WE_RC
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 29/11/2024 to 1700 hrs 29/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1363 MW.
Manager NEM Real Time Operations
[EventId:202411291550_review] Prices for interval 29-Nov-2024 15:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.