121566RESERVE NOTICE07/12/2024 07:13:37 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 07/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121563 is cancelled at 0710 hrs 07/12/2024.

Manager NEM Real Time Operations
     
121563RESERVE NOTICE07/12/2024 06:49:09 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121558 has been updated at 0645 hrs to the following:

[1.] From 1730 hrs 07/12/2024 to 1830 hrs 07/12/2024.
The forecast capacity reserve requirement is 1786 MW.
The minimum capacity reserve available is 1760 MW.

Manager NEM Real Time Operations
     
121558RESERVE NOTICE07/12/2024 04:21:32 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121550 has been updated at 0400 hrs to the following:

[1.] From 1630 hrs 07/12/2024 to 1900 hrs 07/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1284 MW.

Manager NEM Real Time Operations
     
121557NON-CONFORMANCE07/12/2024 03:40:14 AM

NON-CONFORMANCE Region NSW1 Saturday, 7 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 7 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 07/12/2024 03:30 to 07/12/2024 03:40
Amount: -6 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121550RESERVE NOTICE06/12/2024 09:30:33 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1600 hrs 07/12/2024 to 1700 hrs 07/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1126 MW.

Manager NEM Real Time Operations
     
121530RESERVE NOTICE06/12/2024 04:44:35 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121529 is cancelled at 1645 hrs 06/12/2024.

Manager NEM Real Time Operations
     
121529RESERVE NOTICE06/12/2024 04:20:58 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121527 has been updated at 1620 hrs to the following:

[1.] From 1730 hrs 06/12/2024 to 1800 hrs 06/12/2024.
The forecast capacity reserve requirement is 1643 MW.
The minimum capacity reserve available is 1610 MW.

Manager NEM Real Time Operations
     
121527RESERVE NOTICE06/12/2024 03:55:14 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1630 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1626 MW.
The minimum capacity reserve available is 1296 MW.

Manager NEM Real Time Operations
     
121525MARKET INTERVENTION06/12/2024 04:16:05 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121524


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1615 hrs 06/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0700 hrs 07/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/12/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     