123361NON-CONFORMANCE16/01/2025 05:00:21 AM

NON-CONFORMANCE Region NSW1 Thursday, 16 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 16 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 16/01/2025 04:55 to 16/01/2025 05:00
Amount: -21 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123354POWER SYSTEM EVENTS15/01/2025 10:45:07 PM

Non-credible contingency event - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 15/01/2025

At 2019 hrs the Tomago - Taree (963) 132kV line and the Tomago - Brandy Hill (96C) 132kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of disconnection of 80 MW of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123301RESERVE NOTICE15/01/2025 03:56:00 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123295 is cancelled at 1545 hrs 15/01/2025.

Manager NEM Real Time Operations
     
123295RESERVE NOTICE15/01/2025 03:23:56 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123289 has been updated at 1515 hrs to the following:


[1.] From 1630 hrs 15/01/2025 to 1800 hrs 15/01/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1347 MW.


Manager NEM Real Time Operations
     
123293MARKET INTERVENTION15/01/2025 05:01:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123224

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 17/01/2025.

The direction update is issued at 1700 hrs 15/01/2025.

Manager NEM Real Time Operations
     
123292MARKET INTERVENTION15/01/2025 04:58:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123216

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 17/01/2025.

The direction update is issued at 1700 hrs 15/01/2025.

Manager NEM Real Time Operations
     
123256NON-CONFORMANCE15/01/2025 10:15:26 AM

NON-CONFORMANCE Region QLD1 Wednesday, 15 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 15 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/01/2025 09:50 to 15/01/2025 10:15
Amount: 15 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
123249RESERVE NOTICE15/01/2025 08:21:56 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123248 has been updated at 0800 hrs to the following:


[1.] From 1630 hrs 15/01/2025 to 1830 hrs 15/01/2025.
The forecast capacity reserve requirement is 1751 MW.
The minimum capacity reserve available is 1629 MW.


Manager NEM Real Time Operations
     
123248RESERVE NOTICE15/01/2025 07:54:32 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 15/01/2025 to 1800 hrs 15/01/2025.
The forecast capacity reserve requirement is 1765 MW.
The minimum capacity reserve available is 1739 MW.


Manager NEM Real Time Operations
     