Market Notices

121693RESERVE NOTICE10/12/2024 03:08:44 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 1700 hrs to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1310 MW.

AEMO Operations
     
121692RESERVE NOTICE10/12/2024 03:11:22 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 1500 hrs 16/12/2024 to 1630 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

2. From 1930 hrs to 2030 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 962 MW.

AEMO Operations
     
121691MARKET SYSTEMS10/12/2024 02:53:04 PM

CHG0100257 | Production | MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services

Change Number: CHG0100257

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services.

Change Start Date & Time: 12/12/2024 14:00:00 AEST
Change End Date & Time: 12/12/2024 16:00:00 AEST
Outage Start Date & Time: 12/12/2024 15:00:00 AEST
Outage End Date & Time: 12/12/2024 15:01:00 AEST

Environment: Production

Participant Impact and Requirements: During there change, there will be a 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Norwest will not be affected during this time.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
121685MARKET INTERVENTION10/12/2024 08:24:02 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 11/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
121684NON-CONFORMANCE10/12/2024 01:00:18 AM

NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/12/2024 00:55 to 10/12/2024 01:00
Amount: -13 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121652NON-CONFORMANCE09/12/2024 11:15:15 AM

NON-CONFORMANCE Region QLD1 Monday, 9 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 9 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MIDDLSF1
Duration: 09/12/2024 10:25 to 09/12/2024 11:15
Amount: 22 MW
Constraint: NC-Q_MIDDLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121650NON-CONFORMANCE09/12/2024 01:05:13 AM

NON-CONFORMANCE Region NSW1 Monday, 9 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 9 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 09/12/2024 00:40 to 09/12/2024 01:05
Amount: 7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121649NON-CONFORMANCE09/12/2024 12:10:13 AM

NON-CONFORMANCE Region NSW1 Monday, 9 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 8 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 08/12/2024 23:50 to 09/12/2024 00:10
Amount: 6 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121634RESERVE NOTICE08/12/2024 06:17:47 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1830 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 920 MW.

Manager NEM Real Time Operations
     