Market Notices

124310PRICES SUBJECT TO REVIEW07/02/2025 05:30:25 PM

[EventId:202502071735_review] Prices for interval 07-Feb-2025 17:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 7 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124308PRICES SUBJECT TO REVIEW07/02/2025 05:25:15 PM

[EventId:202502071730_review] Prices for interval 07-Feb-2025 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 7 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124307PRICES SUBJECT TO REVIEW07/02/2025 05:20:18 PM

[EventId:202502071725_review] Prices for interval 07-Feb-2025 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 7 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124306PRICES SUBJECT TO REVIEW07/02/2025 05:15:23 PM

[EventId:202502071720_review] Prices for interval 07-Feb-2025 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 7 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124305RESERVE NOTICE07/02/2025 05:21:00 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 936 MW

Manager NEM Real Time Operations
     
124304PRICES SUBJECT TO REVIEW07/02/2025 05:10:28 PM

[EventId:202502071715_review] Prices for interval 07-Feb-2025 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 7 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124303PRICES SUBJECT TO REVIEW07/02/2025 05:05:21 PM

[EventId:202502071710_review] Prices for interval 07-Feb-2025 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 7 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Feb-2025 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124297RESERVE NOTICE07/02/2025 02:01:59 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124290 has been updated to the following:

[1.] From 1630 hrs 07/02/2025 to 1900 hrs 07/02/2025.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1034 MW.

Manager NEM Real Time Operations
     
124290RESERVE NOTICE07/02/2025 08:18:59 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1185 MW.