Market Notices

123806SETTLEMENTS RESIDUE28/01/2025 11:45:29 AM

[EventId:202501281145_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 28 January 2025 11:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 28 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1145 hrs on 28 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123805SETTLEMENTS RESIDUE28/01/2025 10:30:32 AM

[EventId:202501281030_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 28 January 2025 10:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 28 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 28 January 2025.

Refer to market notice: 123802

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1030 hrs on 28 January 2025.

This is an AEMO autogenerated Market Notice.
     
123804GENERAL NOTICE28/01/2025 10:36:56 AM

NEM Local Temperature Alerts for NSW, VIC from 28 Jan 2025 to 01 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

NSW
Sydney Observatory Hill (39+ Deg C): 28th Jan
Yass (39+ Deg C): 28th Jan

VIC
Mildura Ap (39+ Deg C): 1st Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123803RESERVE NOTICE28/01/2025 10:43:22 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123773 is cancelled at 1030 hrs 28/01/2025.

Manager NEM Real Time Operations
     
123802SETTLEMENTS RESIDUE28/01/2025 09:15:27 AM

[EventId:202501280915_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 28 January 2025 09:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0915 hrs on 28 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 28 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0915 hrs on 28 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123801RECLASSIFY CONTINGENCY28/01/2025 12:14:40 AM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 28/01/2025 00:14

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 123795

Auto-generated on behalf of Manager NEM Real Time Operations
     
123800RECLASSIFY CONTINGENCY27/01/2025 09:34:38 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 27/01/2025 21:34

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 123760

Auto-generated on behalf of Manager NEM Real Time Operations
     
123799RECLASSIFY CONTINGENCY27/01/2025 09:19:40 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 27/01/2025 21:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 123796

Auto-generated on behalf of Manager NEM Real Time Operations
     
123798RECLASSIFY CONTINGENCY27/01/2025 08:49:43 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 27/01/2025 20:49

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 123756