Filter by category
Filter by Date
Forecast Minimum System Load (MSL1) condition in the VIC region on 21/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 21/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1705 MW
o MSL2 - 1205 MW
o MSL3 - 705 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1330 hrs 21/12/2024. Minimum regional demand is forecast to be 1643 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122096 has been updated to the following:
[1.] From 1600 hrs 17/12/2024 to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 996 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122071 has been updated to the following:
[1.] From 1530 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 815 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122007 has been updated to the following:
[1.] From 1430 hrs 17/12/2024 to 1530 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 907 MW.
[2.] From 1800 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1012 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024
Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.122029 is cancelled at 1835 hrs 16/12/2024.
Manager NEM Real Time Operations
[EventId:202412161745_review] Prices for interval 16-Dec-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161740_review] Prices for interval 16-Dec-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161735_review] Prices for interval 16-Dec-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161730_review] Prices for interval 16-Dec-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.