Filter by category
Filter by Date
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124394
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1030 hrs 11/02/2025.
The direction update is issued at 1530 hrs 10/02/2025.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
NEM Local Temperature Alerts for SA, VIC from 10 Feb 2025 to 14 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 11th Feb, 12th Feb
Clare High School (39+ Deg C): 12th Feb
Mt Gambier Ap (39+ Deg C): 12th Feb
Port Augusta Ap (39+ Deg C): 11th Feb, 12th Feb
VIC
Mildura Ap (39+ Deg C): 12th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124396
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 10/02/2025.
The direction update is issued at 0810 hrs 10/02/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124357
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 11/02/2025.
The direction update is issued at 1600 hrs 09/02/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124358
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 11/02/2025.
The direction update is issued at 1600 hrs 09/02/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124254
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 10/02/2025.
The direction update is issued at 1415 hrs 08/02/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124255
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 10/02/2025.
The direction update is issued at 1415 hrs 08/02/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124254
PPCCGT PELICAN POINT at 0730 hrs 07/02/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 09/02/2025.
The direction update is issued at 1410 hrs 07/02/2025.
Manager NEM Real Time Operations