Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 124096
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 05/02/2025.
The direction update is issued at 1315 hrs 05/02/2025.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124150 has been updated at 1200 hrs 05/02/2025 to the following:
From 1730 hrs to 1830 hrs 07/02/2025.
The forecast capacity reserve requirement is 1063 MW.
The minimum capacity reserve available is 967 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124143 has been updated at 1000 hrs 05/02/2025 to the following:
From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1161 MW.
The minimum capacity reserve available is 883 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124147 is cancelled at 1000 hrs 05/02/2025.
No LOR2 condition is currently forecast in the SA region in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1800 hrs to 2030 hrs 11/02/2025.
The forecast capacity reserve requirement is 222 MW.
The minimum capacity reserve available is 180 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124066 has been updated at 0423 hrs 05/02/2025 to the following:
[1.] From 1600 hrs 07/02/2025 to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1144 MW.
The minimum capacity reserve available is 678 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 04/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124121 is cancelled at 1715 hrs 04/02/2025.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 04/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124090 has been updated at 1620 hrs 04/02/2025 to the following:
[1.] From 1730 hrs 04/02/2025 to 1830 hrs 04/02/2025.
The forecast capacity reserve requirement is 948 MW.
The minimum capacity reserve available is 664 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Direction - SA region 04/02/2025
Direction - SA region 04/02/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1545 hrs on 04/02/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations