PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 08/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125374 is cancelled at 1345 hrs 08/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 09/03/2025 to 1930 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 593 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025
Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025
At 0720 hrs 07/03/2025 there was an unplanned outage of Lismore SVC.
The following constraint set(s) invoked at 0725 hrs 07/03/2025
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Refer to Market Notice 125355.
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 and 2 cables of Directlink .
The following constraint set was invoked at 0620 hrs 07/03/2025
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 07/03/2025
Non-credible contingency event - NSW region - 07/03/2025
At 0612 hrs the following plant tripped.
Lismore132 - Mullumbimby 9U6 132kV Line
Lismore132 - Mullumbimby 9U7 132kV Line
Ewingsdale - Mullumbimby 9G5 132kV Line
No 1 and 2 cables of Directlink
AEMO did not instruct load shedding.
Approximately 7MW of bulk electrical load has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No. 1 and 2 Legs of Directlink.
The following constraint set was invoked at 1125 hrs 06/03/2025.
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/03/2025 to 1600 hrs 06/03/2025.
The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1635 hrs 05/03/2025
Constraint set(s) revoked: N-LDTM_82
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Ewingsdale-Mullumbimby 9G5 132kV line - NSW region - 05/03/2025
Inter-regional transfer limit variation - Ewingsdale-Mullumbimby 9G5 132kV line - NSW region - 05/03/2025
At 1603 hrs 05/03/2025 there was an unplanned outage of Ewingsdale-Mullumbimby 9G5 132kV line.
The following constraint set(s) invoked at 1615 hrs 05/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 05/03/2025
Update - Non-credible contingency event - NSW region - 05/03/2025
Refer AEMO Electricity Market Notice 125268
At 1400 hrs the Directlink DC1 was returned to service.
(At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line was returned to service.)
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations