Filter by category
Filter by Date
Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121024 has been updated at 1000 hrs 28/11/2024 to the following:
1. From 1100 hrs to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1332 MW.
The minimum capacity reserve available is 1171 MW.
2. From 1530 hrs to 1700 hrs 29/11/2024.
The forecast capacity reserve requirement is 1205 MW.
The minimum capacity reserve available is 1126 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121106 is cancelled at 2000 hrs 27/11/2024.
Manager NEM Real Time Operations
End of RERT Dispatch - 27/11/2024 and End of intervention event
End of Reliability and Emergency Reserve Trader (RERT) dispatch for - NSW1 Region - 27/11/2024 and end of AEMO Intervention Event.
Refer AEMO Electricity Market Notices 121102
Activation of reserve contract(s) has ended.
The reserve contract(s) were activated from 15:45 hrs 27/11/2024 to 16:45 hrs 27/11/2024
The AEMO Intervention Event ended from 16:45 hrs 27/11/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - NSW region 27/11/2024
Cancellation - AEMO Intervention Event - NSW region 27/11/2024
Refer to Market Notice 121070
The AEMO Intervention Event and all associated directions are cancelled from 1645 hrs on 27/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1
Cancellation: Direction issued to: Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1
Refer to Market Notice 121083
Direction is cancelled from: 1645 hrs 27/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS
Cancellation: Direction issued to: Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS
Refer to Market Notice 121067
Direction is cancelled from: 1645 hrs 27/11/2024
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121089 has been updated at 1645 hrs to the following:
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 859 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121066 is cancelled at 1530 hrs 27/11/2024.
Manager NEM Real Time Operations