Market Notices

123647SETTLEMENTS RESIDUE24/01/2025 08:10:22 AM

[EventId:202501240810_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 January 2025 08:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0810 hrs on 24 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0810 hrs on 24 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123646MARKET SYSTEMS24/01/2025 07:21:37 AM

CHG0100766 | Completed | Production | Planned Maintenance to Brisbane ISE Server

Change Number: CHG0100766
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Planned Maintenance to Brisbane ISE Server
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
123643RESERVE NOTICE23/01/2025 11:42:20 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the Qld region advised in AEMO Electricity Market Notice No. 123636 is cancelled at 2340 hrs 23/01/2025

Manager NEM Real Time Operations
     
123636RESERVE NOTICE23/01/2025 05:22:27 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 123625 has been updated at 1700 hrs to the following:

[1.] From 1800 hrs 24/01/2025 to 1900 hrs 24/01/2025.
The forecast capacity reserve requirement is 813 MW.
The minimum capacity reserve available is 751 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
123625RESERVE NOTICE23/01/2025 01:24:08 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1800 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 816 MW.
The minimum capacity reserve available is 572 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
123624MARKET INTERVENTION23/01/2025 02:57:06 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123579

TORRB3 TORRENS ISLAN at 0400 hrs 24/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/01/2025.

The direction update is issued at 1500 hrs 23/01/2025.

Manager NEM Real Time Operations
     
123623MARKET INTERVENTION23/01/2025 02:55:48 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123618

PPCCGT PELICAN POINT at 1800 hrs 23/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1730 hrs 24/01/2025.

The direction update is issued at 1500 hrs 23/01/2025.

Manager NEM Real Time Operations
     
123620RESERVE NOTICE23/01/2025 10:40:22 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 123619 is cancelled at 1000 hrs 23/01/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
123619RESERVE NOTICE23/01/2025 10:09:52 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 863 MW.
The minimum capacity reserve available is 825 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     