Filter by category
Filter by Date
NEM Local Temperature Alerts for QLD from 27 Dec 2024 to 31 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 28th Dec, 29th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122472
The PPCCGT PELICAN POINT direction is now expected to stay in place until 2230 hrs 27/12/2024.
The direction update is issued at 1700 hrs 26/12/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122468
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 28/12/2024.
The direction update is issued at 1630 hrs 26/12/2024.
Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Update to Market Notice 122466 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1660 MW
- MSL2 - 1160 MW
- MSL3 - 660 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 01/01/2025 to 1330 hrs 01/01/2025. Minimum regional demand is forecast to be 1474 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 29/12/2024
Forecast Minimum System Load MSL1 condition in the VIC Region on 29/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 29/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1730 MW
- MSL2 - 1230 MW
- MSL3 - 730 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 29/12/2024 to 1400 hrs 29/12/2024. Minimum regional demand is forecast to be 1489 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122451
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1700 hrs 25/12/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2330 hrs 25/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 27/12/2024.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122453
Direction is cancelled from: 1600 hrs 25/12/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122459
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/12/2024.
The direction update is issued at 1700 hrs 25/12/2024.
Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1660 MW
- MSL2 - 1160 MW
- MSL3 - 660 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1030 hrs 01/01/2025 to 1430 hrs 01/01/2025. Minimum regional demand is forecast to be 1422 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations